NJ Energy Code (856) 569-1010 Check

Duct Systems

Duct Insulation

The 2018 IRC/IECC now requires equal insulation levels on supply and return ducts, but the R-value depends on size and location:

Duct Sealing

Like the 2015 version, the 2018 IRC/IECC requires that all ducts, air handlers, and filter boxes be sealed.

Sealing must follow the details in the 2018 IRC, which allows the use of mastics, liquid sealants, and tapes.  The 2018 IECC also allows the use of air-impermeable spray foam products as both duct insulation and sealant.

Duct Mastic Photo

Air handlers must be designated for leakage of no more than 2% of the design air flow rate (per ASHRAE 193).

Duct Leakage Testing

If any ducts are outside the thermal envelope, a duct blaster test must be conducted to determine the Total Leakage.

Duct Blaster Photo

The 2015 IRC/IECC specifies different leakage limits depending on the test conditions.  In all cases the limits are based on the conditioned floor area (CFA) of the house:

Total Leakage Limits Table

(Note:  these limits only apply to projects following a prescriptive compliance pathway.  Projects following a performance or ERI pathway are allowed to trade off higher duct leakage for improved performance in other areas.)

For ducts to all be considered "within the building thermal envelope", they must be on the interior side of both the insulation and air barrier. Therefore, if any ducts are located in attics, vented crawlspaces, or exterior wall cavities, the system must be tested and meet the leakage requirements.

 

NO Panned Returns!

The 2018 IRC/IECC does not allow building cavities to be used as ducts.
 Panned Return Graphic
 

Local Energy Audits Interested in our Services?